Capacity: 250 t/h
4 off 4,600 m2 pre-concentrators
with individual recompressor
Drives: 4*1,2 MW
Finisher:
quadruple-effect evaporator revamped by GIG
Construction period: 7 months from effective contract date to start-up 1/2 month after start-up in operation with 100 %
performance